By: Michael Horoho | Date: 11/14/2026 02:45:25 PM
Hopefully, this will clarify some of the questions and comments regarding our email concerning INDOT acquiring a portion of our property at the front entrance to accommodate the planned Highway 32 project of widening the Highway to 4 lanes.
The Highway 32 project has been in the plan and design phase for over 2 years now and they have reached the planned project portion. In order to accommodate the planned project, INDOT needed to acquire 401 square feet of right of way at the Trailside Woods entrance and 1044 square feet of temporary right-of-way easement located in the brush and wooded area behind and between the homes located at 5256 Tulip Tree drive and 5270 Tulip Tree Drive. The land being acquired at the front entrance is the two small grass beds behind the stop sign on the east side of the entrance and a small sliver of land located next to our entrance sign on the west side. The planned project has a Do not Disturb attached to our sign which means the sign is not to be touched in any way.
Our sign and street light at the entrance are sitting on a right of way currently owned by the City of Noblesville and Trailside Woods has an encroachment agreement with the city to allow the sign to be there. The project plan shows that the planned trail associated with the road widening will be located a few feet north of our light pole at the front entrance and a connection will be made from the planned trail to our existing trail on the east side of the entrance. Most of our purchased land at the front entrance is for easement. The initial offer from INDOT for that section of land was $4,300 dollars. The temporary right-of-way easement that INDOT is acquiring from Trailside Woods near the new roundabout and entrance road to the school is giving INDOT temporary access if needed while they construct the roundabout and new road. They may have to remove some of the brush or small trees near the grassy area of the school for infrastructure or drainage, but the new road is not being constructed in that wooded area. The plans show the roundabout and new road being constructed in the grassy area that is located at the current front entrance to the school. After completion of the project, Trailside Woods will resume total ownership of the land. The initial offer from INDOT for the temporary easement was $800.
The Board countered the initial offer of $5,100 with a counter proposal of $7,000 to include additional funds to help add 3 small trees to the berm located between 5256 & 5270 Tulip Tree Drive as an additional sight and sound barrier if needed. This was the potential sound barrier that was referenced in the earlier email and not an actual wall. We also stated in our counter proposal that the additional funds were necessary along with initial offer to replace the displaced landscaping and to enhance the area near the entrance with the new trail. INDOT accepted our counter offer after we submitted it.
The Board worked very closely with the INDOT representative associated with this project and had assistance from a former employee of INDOT who had worked previously within this same department.